Optimize Solar kWp Distribution

Home / Optimize Solar KWp Distribution

Conclusion:

  • Solar kWp generation & distribution remain consistent @300kWp per day (assume dependent variable factor are constant).

  • Due to inefficiency, the 300kWp generation can only being transmitted to 2 units of AHU

  • The oter AHU units will depend on grid supply (TNB). Thus, it will increase overall TNB bills.

  • An installation of PFCS will correct the power factor at incoming and outgoing levels consequently increase a distribution capacity and reduce TNB bills by 20-30%

Process of Calculation Formula